The MASSACHUSETTS PORT AUTHORITY is soliciting Statements of Qualifications from TRADE CONTRACTORS interested in performing work for L1429-C1 TERMINAL C ENHANCEMENT PROJECTS The Authority is seeking Qualification Statements from Trade Contractors who have a demonstrated experience in the construction and implementation of similar work in terms of scale and complexity as required for the Terminal C Pier B In accordance with Massachusetts construction manager at-risk requirements, MGL Chapter 149A Section 8, Qualification Statements are being requested from trade contractors capable of performing the following classes of work: Masonry; Miscellaneous and Ornamental Iron; Waterproofing, Damproofing & Caulking; Roofing and Flashing; Tile; Acoustical Tile; Terrazzo; Painting; Fire Protection; Plumbing; HVAC; Electrical.

The contract includes the following scope of work: Terminal C Enhancement Project is one component for the optimization of Terminal C at Pier B. Scope of work includes demolition of the arrivals level of Pier B located between gate C14 to C21 across from gates C19 and C20 and a two story infill will be built in its place to enhance departures level passenger amenities with new public toilets, companion care room, nursing room, service animal relief area, additional concessions and arrivals level tenant space. Construction of new passenger amenity space will require careful phasing to ensure airline operations will not be interrupted in order to enable the continuous use of gates C14, C19, C20 and C21 during construction. The first phase of the project will include demolition of existing arrivals level tenant space, followed with construction of two story infill space.

The estimated cost of the trade contractors’ portion of this phase of the Project is approximately $2,221,000 and the construction duration for this phase is approximately 9 months. The estimated value of work to be performed by trade contractors is as follows:

Masonry $93,000

Miscellaneous and Ornamental Iron $47,000

Waterproofing, Damproofing & Caulking $45,000

Roofing and Flashing $206,000

Tile $177,000

Acoustical Tile $96,000

Terrazzo $168,000

Painting $42,000

Fire Protection $167,000

Plumbing $412,000

HVAC $493,000

Electrical $275,000

The Authority is implementing this project in accordance with MGL Chapter 149A, Sections 1 thru 13. This selection of trade contractors conforms to MGL Chapter 149A, Section 8, subsections (b) to (k) inclusive. This Request for Qualifications (RFQ) will be utilized to prequalify trade contractors capable and experienced in the construction of parking garages and terminal buildings. The Authority shall utilize a two-step process including the prequalification of trade contractors based on an evaluation of the Statement of Qualifications received in response to this solicitation, followed by an Invitation to Bidders that will only be issued to the prequalified trade contractors. A Prequalification Committee consisting of four representatives, one each from the Designer and the CM at Risk and two Massport staff. This Prequalification Committee will be conducting a qualifications-based evaluation of submittals received from interested trade contractors in order to identify prequalified trade contractors who will be invited to respond to a written Invitation to Bidders. Please note that the Authority is not utilizing this process to prequalify subcontractors who are not trade contractors which shall be done separately in accordance with MGL C149A, Section 8, subsection (j).